Last Week's Plan
Phani
  • Puf & Gni bugs - Left with known 22 bugs and enhancements
  • Product Page - Completed
  • Integration of sharad and vamsi work -Completed with sharad
  • Integration of livechat with live tracker - Not started
Sharad
  • Gni Shopping cart bugs -Completed
  • Gni Checkout without login -Not Completed
Vamsi
  • DHTML Menu -Completed
  • PUF variants and Configurable products - Not Completed
  • SFMS Log error -Not Started
  • OFBIZ optimization -Not Started
This Week's Plan
Phani
  • Ofbiz optimisation
  • Intgeration of livechat
Sharad
  • Gni Checkout without login
  • PUF and GNI Bugs
Vamsi
  • PUF variants and Configurable products
  • PUF and GNI Bugs